Commission Regulation (EU) 2016/1447 of 26 August 2016 establishing a network cod... (32016R1447) 
                
                
            INHALT
Commission Regulation (EU) 2016/1447 of 26 August 2016 establishing a network code on requirements for grid connection of high voltage direct current systems and direct current-connected power park modules (Text with EEA relevance)
- COMMISSION REGULATION (EU) 2016/1447
 - of 26 August 2016
 - establishing a network code on requirements for grid connection of high voltage direct current systems and direct current-connected power park modules
 - (Text with EEA relevance)
 - TITLE I
 - GENERAL PROVISIONS
 - Article 1
 - Subject matter
 - Article 2
 - Definitions
 - Article 3
 - Scope of application
 - Article 4
 - Application to existing HVDC systems and DC-connected power park modules
 - Article 5
 - Regulatory aspects
 - Article 6
 - Multiple TSOs
 - Article 7
 - Recovery of costs
 - Article 8
 - Public consultation
 - Article 9
 - Stakeholder involvement
 - Article 10
 - Confidentiality obligations
 - TITLE II
 - GENERAL REQUIREMENTS FOR HVDC CONNECTIONS
 - CHAPTER 1
 - Requirements for active power control and frequency support
 - Article 11
 - Frequency ranges
 - Article 12
 - Rate-of-change-of-frequency withstand capability
 - Article 13
 - Active power controllability, control range and ramping rate
 - Article 14
 - Synthetic inertia
 - Article 15
 - Requirements relating to frequency sensitive mode, limited frequency sensitive mode overfrequency and limited frequency sensitive mode underfrequency
 - Article 16
 - Frequency control
 - Article 17
 - Maximum loss of active power
 - CHAPTER 2
 - Requirements for reactive power control and voltage support
 - Article 18
 - Voltage ranges
 - Article 19
 - Short circuit contribution during faults
 - Article 20
 - Reactive power capability
 - Article 21
 - Reactive power exchanged with the network
 - Article 22
 - Reactive power control mode
 - Article 23
 - Priority to active or reactive power contribution
 - Article 24
 - Power quality
 - CHAPTER 3
 - Requirements for fault ride through capability
 - Article 25
 - Fault ride through capability
 - Article 26
 - Post fault active power recovery
 - Article 27
 - Fast recovery from DC faults
 - CHAPTER 4
 - Requirements for control
 - Article 28
 - Energisation and synchronisation of HVDC converter stations
 - Article 29
 - Interaction between HVDC systems or other plants and equipment
 - Article 30
 - Power oscillation damping capability
 - Article 31
 - Subsynchronous torsional interaction damping capability
 - Article 32
 - Network characteristics
 - Article 33
 - HVDC system robustness
 - CHAPTER 5
 - Requirements for protection devices and settings
 - Article 34
 - Electrical protection schemes and settings
 - Article 35
 - Priority ranking of protection and control
 - Article 36
 - Changes to protection and control schemes and settings
 - CHAPTER 6
 - Requirements for power system restoration
 - Article 37
 - Black start
 - TITLE III
 - REQUIREMENTS FOR DC-CONNECTED POWER PARK MODULES AND REMOTE-END HVDC CONVERTER STATIONS
 - CHAPTER 1
 - Requirements for DC-connected power park modules
 - Article 38
 - Scope
 - Article 39
 - Frequency stability requirements
 - Article 40
 - Reactive power and voltage requirements
 - Article 41
 - Control requirements
 - Article 42
 - Network characteristics
 - Article 43
 - Protection requirements
 - Article 44
 - Power quality
 - Article 45
 - General system management requirements applicable to DC-connected power park modules
 - CHAPTER 2
 - Requirements for remote-end HVDC converter stations
 - Article 46
 - Scope
 - Article 47
 - Frequency stability requirements
 - Article 48
 - Reactive power and voltage requirements
 - Article 49
 - Network characteristics
 - Article 50
 - Power quality
 - TITLE IV
 - INFORMATION EXCHANGE AND COORDINATION
 - Article 51
 - Operation of HVDC systems
 - Article 52
 - Parameters and settings
 - Article 53
 - Fault recording and monitoring
 - Article 54
 - Simulation models
 - TITLE V
 - OPERATIONAL NOTIFICATION PROCEDURE FOR CONNECTION
 - CHAPTER 1
 - Connection of new HVDC systems
 - Article 55
 - General provisions
 - Article 56
 - EON for HVDC systems
 - Article 57
 - ION for HVDC systems
 - Article 58
 - FON for HVDC systems
 - Article 59
 - Limited operational notification for HVDC systems/derogations
 - CHAPTER 2
 - Connection of new DC-connected power park modules
 - Article 60
 - General provisions
 - Article 61
 - EON for DC-connected power park modules
 - Article 62
 - ION for DC-connected power park modules
 - Article 63
 - FON for DC-connected power park modules
 - Article 64
 - Limited operational notification for DC-connected power park modules
 - CHAPTER 3
 - Cost benefit analysis
 - Article 65
 - Identification of costs and benefits of application of requirements to existing HVDC systems or DC-connected power park modules
 - Article 66
 - Principles of cost-benefit analysis
 - TITLE VI
 - COMPLIANCE
 - CHAPTER 1
 - Compliance monitoring
 - Article 67
 - Common provisions for compliance testing
 - Article 68
 - Common provisions on compliance simulation
 - Article 69
 - Responsibility of the HVDC system owner and DC-connected power park module owner
 - Article 70
 - Tasks of the relevant system operator
 - CHAPTER 2
 - Compliance testing
 - Article 71
 - Compliance testing for HVDC systems
 - Article 72
 - Compliance testing for DC-connected power park modules and remote-end HVDC converter units
 - CHAPTER 3
 - Compliance simulations
 - Article 73
 - Compliance simulations for HVDC systems
 - Article 74
 - Compliance simulations for DC-connected power park modules and remote-end HVDC converter units
 - CHAPTER 4
 - Non-binding guidance and monitoring of implementation
 - Article 75
 - Non-binding guidance on implementation
 - Article 76
 - Monitoring
 - TITLE VII
 - DEROGATIONS
 - Article 77
 - Power to grant derogations
 - Article 78
 - General provisions
 - Article 79
 - Request for derogations by an HVDC system owner or DC-connected power park module owner
 - Article 80
 - Request for a derogation by a relevant system operator or relevant TSO
 - Article 81
 - Request for derogations from the provisions of Title III by a DC-connected power park module owner
 - Article 82
 - Register of derogations from the requirements of this Regulation
 - Article 83
 - Monitoring of derogations
 - TITLE VIII
 - FINAL PROVISIONS
 - Article 84
 - Amendment of contracts and general terms and conditions
 - Article 85
 - HVDC System or DC-connected power park modules connecting with synchronous areas or control areas not bound by EU legislation
 - Article 86
 - Entry into force
 - ANNEX I
 - Frequency ranges referred to in Article 11
 - ANNEX II
 - Requirements applying to frequency sensitive mode, limited frequency sensitive mode overfrequency and limited frequency sensitive mode underfrequency
 - A. Frequency sensitive mode
 - B. Limited frequency sensitive mode overfrequency
 - C. Limited frequency sensitive mode underfrequency
 - ANNEX III
 - Voltage ranges referred to in Article 18
 - ANNEX IV
 - Requirements for U-Q/Pmax-profile referred to in Article 20
 - ANNEX V
 - Voltage-against-time-profile referred to in Article 25
 - ANNEX VI
 - Frequency ranges and time periods referred to in Article 39(2)(a)
 - ANNEX VII
 - Voltage ranges and time periods referred to in Article 40
 - ANNEX VIII
 - Reactive power and voltage requirements referred to in Article 48