Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code ... (32016R0631) 
                
                
            INHALT
Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code on requirements for grid connection of generators (Text with EEA relevance)
- COMMISSION REGULATION (EU) 2016/631
 - of 14 April 2016
 - establishing a network code on requirements for grid connection of generators
 - (Text with EEA relevance)
 - TITLE I
 - GENERAL PROVISIONS
 - Article 1
 - Subject matter
 - Article 2
 - Definitions
 - Article 3
 - Scope of application
 - Article 4
 - Application to existing power-generating modules
 - Article 5
 - Determination of significance
 - Article 6
 - Application to power-generating modules, pump-storage power-generating modules, combined heat and power facilities, and industrial sites
 - Article 7
 - Regulatory aspects
 - Article 8
 - Multiple TSOs
 - Article 9
 - Recovery of costs
 - Article 10
 - Public consultation
 - Article 11
 - Stakeholder involvement
 - Article 12
 - Confidentiality obligations
 - TITLE II
 - REQUIREMENTS
 - CHAPTER 1
 - General requirements
 - Article 13
 - General requirements for type A power-generating modules
 - Figure 1
 - Active power frequency response capability of power-generating modules in LFSM-O
 - Figure 2
 - Maximum power capability reduction with falling frequency
 - Article 14
 - General requirements for type B power-generating modules
 - Figure 3
 - Fault-ride-through profile of a power-generating module
 - Article 15
 - General requirements for type C power-generating modules
 - Figure 4
 - Active power frequency response capability of power-generating modules in LFSM-U
 - Figure 5
 - Active power frequency response capability of power-generating modules in FSM illustrating the case of zero deadband and insensitivity
 - Figure 6
 - Active power frequency response capability
 - Article 16
 - General requirements for type D power-generating modules
 - CHAPTER 2
 - Requirements for synchronous power-generating modules
 - Article 17
 - Requirements for type B synchronous power-generating modules
 - Article 18
 - Requirements for type C synchronous power-generating modules
 - Figure 7
 - U-Q/P
 - max
 - -profile of a synchronous power-generating module
 - Article 19
 - Requirements for type D synchronous power-generating modules
 - CHAPTER 3
 - Requirements for power park modules
 - Article 20
 - Requirements for type B power park modules
 - Article 21
 - Requirements for type C power park modules
 - Figure 8
 - U-Q/P
 - max
 - -profile of a power park module
 - Figure 9
 - P-Q/P
 - max
 - -profile of a power park module
 - Article 22
 - Requirements for type D power park modules
 - CHAPTER 4
 - Requirements for offshore power park modules
 - Article 23
 - General provisions
 - Article 24
 - Frequency stability requirements applicable to AC-connected offshore power park modules
 - Article 25
 - Voltage stability requirements applicable to AC-connected offshore power park modules
 - Article 26
 - Robustness requirements applicable to AC-connected offshore power park modules
 - Article 27
 - System restoration requirements applicable to AC-connected offshore power park modules
 - Article 28
 - General system management requirements applicable to AC-connected offshore power park modules
 - TITLE III
 - OPERATIONAL NOTIFICATION PROCEDURE FOR CONNECTION
 - CHAPTER 1
 - Connection of new power-generating modules
 - Article 29
 - General provisions
 - Article 30
 - Operational notification of type A power-generating modules
 - Article 31
 - Operational notification of type B, C and D power-generating modules
 - Article 32
 - Procedure for type B and C power-generating modules
 - Article 33
 - Procedure for type D power-generating modules
 - Article 34
 - Energisation operational notification for type D power-generating modules
 - Article 35
 - Interim operational notification for type D power-generating modules
 - Article 36
 - Final operational notification for type D power-generating modules
 - Article 37
 - Limited operational notification for type D power-generating modules
 - CHAPTER 2
 - Cost-benefit analysis
 - Article 38
 - Identification of costs and benefits of application of requirements to existing power-generating modules
 - Article 39
 - Principles of cost-benefit analysis
 - TITLE IV
 - COMPLIANCE
 - CHAPTER 1
 - Compliance monitoring
 - Article 40
 - Responsibility of the power-generating facility owner
 - Article 41
 - Tasks of the relevant system operator
 - Article 42
 - Common provisions for compliance testing
 - Article 43
 - Common provisions on compliance simulation
 - CHAPTER 2
 - Compliance testing for synchronous power-generating modules
 - Article 44
 - Compliance tests for type B synchronous power-generating modules
 - Article 45
 - Compliance tests for type C synchronous power-generating modules
 - Article 46
 - Compliance tests for type D synchronous power-generating modules
 - CHAPTER 3
 - Compliance testing for power park modules
 - Article 47
 - Compliance tests for type B power park modules
 - Article 48
 - Compliance tests for type C power park modules
 - Article 49
 - Compliance tests for type D power park modules
 - CHAPTER 4
 - Compliance testing for offshore power park modules
 - Article 50
 - Compliance tests for offshore power park modules
 - CHAPTER 5
 - Compliance simulations for synchronous power-generating modules
 - Article 51
 - Compliance simulations for type B synchronous power-generating modules
 - Article 52
 - Compliance simulations for type C synchronous power-generating modules
 - Article 53
 - Compliance simulations for type D synchronous power-generating modules
 - CHAPTER 6
 - Compliance simulations for power park modules
 - Article 54
 - Compliance simulations for type B power park modules
 - Article 55
 - Compliance simulations for type C power park modules
 - Article 56
 - Compliance simulations for type D power park modules
 - CHAPTER 7
 - Compliance simulations for offshore power park modules
 - Article 57
 - Compliance simulations applicable to offshore power park modules
 - CHAPTER 8
 - Non-binding guidance and monitoring of implementation
 - Article 58
 - Non-binding guidance on implementation
 - Article 59
 - Monitoring
 - TITLE V
 - DEROGATIONS
 - Article 60
 - Power to grant derogations
 - Article 61
 - General provisions
 - Article 62
 - Request for a derogation by a power-generating facility owner
 - Article 63
 - Request for a derogation by a relevant system operator or relevant TSO
 - Article 64
 - Register of derogations from the requirements of this Regulation
 - Article 65
 - Monitoring of derogations
 - TITLE VI
 - TRANSITIONAL ARRANGEMENTS FOR EMERGING TECHNOLOGIES
 - Article 66
 - Emerging technologies
 - Article 67
 - Establishment of thresholds for classification as emerging technologies
 - Article 68
 - Application for classification as an emerging technology
 - Article 69
 - Assessment and approval of requests for classification as an emerging technology
 - Article 70
 - Withdrawal of classification as an emerging technology
 - TITLE VII
 - FINAL PROVISIONS
 - Article 71
 - Amendment of contracts and general terms and conditions
 - Article 72
 - Entry into force