Commission Implementing Decision (EU) 2022/2520 of 20 December 2022 on the specific arrangements for the handover and takeover process of the e-CODEX system (Text with EEA relevance)
- COMMISSION IMPLEMENTING DECISION (EU) 2022/2520
 - of 20 December 2022
 - on the specific arrangements for the handover and takeover process of the e-CODEX system
 - (Text with EEA relevance)
 - Article 1
 - Article 2
 - Article 3
 - Article 4
 - ANNEX
 - Specific arrangements for the handover and takeover process of the e-CODEX system
 - 1.
 - INTRODUCTION
 - 2.
 - MAIN MILESTONES
 - 3.
 - HANDOVER AND TAKEOVER ACTIVITIES
 - 4.
 - ACTIVITIES
 - (a)
 - Training Activities
 - (b)
 - Transparency of the handover and takeover process
 - (c)
 - Responsibility of eu-LISA and the entity managing the e-CODEX system during the handover and takeover process
 - 5.
 - CRITERIA FOR A SUCCESSFUL HANDOVER PROCESS
 - 6.
 - CRITERIA FOR A SUCCESSFUL TAKEOVER PROCESS
 - 7.
 - INTELLECTUAL PROPERTY RIGHTS OR USAGE RIGHTS
 - 8.
 - TIMELINE
 - 9.
 - STRUCTURE OF THE HANDOVER REPORT TO BE PROVIDED BY THE ENTITY MANAGING THE e-CODEX SYSTEM
 - 10.
 - STRUCTURE OF THE TAKEOVER REPORT TO BE PROVIDED BY eu-LISA
 - APPENDIX
 - COMMON HANDOVER DOCUMENT STRUCTURE
 - Document change log
 - 1.
 - REFERENCE AND APPLICABLE DOCUMENTS
 - 1.1.
 - Reference documents
 - 1.2.
 - Applicable documents
 - 2.
 - TERMINOLOGY
 - 2.1.
 - Abbreviations and acronyms
 - 3.
 - INTRODUCTION
 - 3.1.
 - Purpose of the Document
 - 3.2.
 - Target Audience
 - 4.
 - ASSUMPTIONS AND RISKS
 - 4.1.
 - Assumptions and Prerequisites
 - 4.2.
 - Risks
 - 5.
 - HANDOVER AND TAKEOVER APPROACH
 - 5.1.
 - Kick-Off meeting
 - 5.2.
 - Synchronisation meetings
 - 5.3.
 - Handover Plan
 - 5.4.
 - Initial Handover of assets
 - 5.4.1.
 - Applications
 - 5.4.2.
 - Documentation
 - 5.4.3.
 - Procedures
 - 5.4.4.
 - Backlog (RfC, Tickets, Issues, etc.…)
 - 6.
 - FINAL HANDOVER OF ASSETS
 - 6.1.
 - Applications
 - 6.2.
 - Documentation
 - 6.3.
 - Procedures
 - 6.4.
 - Backlog (RfC, Tickets, Issues, etc.)
 - 7.
 - KNOWLEDGE TRANSFER
 - 8.
 - HANDOVER CONTACT DETAILS
 - 9.
 - TAKEOVER CONTACT DETAILS
 - 10.
 - INFRASTRUCTURE NEEDS AT EU-LISA
 - 10.1. Applications
 - 10.2. Hardware/System Requirements
 - 10.3. COTS (commercial off-the-shelf)
 - 11.
 - SECURITY REQUIREMENTS
 - 12.
 - WORKSHOP SCHEDULE
 - 12.1.
 - General workshop about all services
 - 12.2.
 - Helpdesk and Operations Workshops
 - 12.3.
 - Installation and Testing Workshops
 - 12.3.1.
 - Installations
 - 12.3.2.
 - Testing
 - 12.3.3.
 - Workshops on other topics
 - 12.3.4.
 - Q&A and Shadowing Workshops
 - 13.
 - CRITERIA FOR A SUCCESSFUL HANDOVER PROCESS AND FOR THE SUCCESSFUL COMPLETION OF THAT PROCESS
 - 14.
 - SHADOWING PERIOD, TRANSFER OF RESPONSIBILITY AND AFTER-CARE PERIOD
 - 15.
 - PLANNING
 - 15.1.
 - High-level Planning
 - 15.2.
 - Detailed Planning
 - 16.
 - TAKEOVER TEST PLAN
 - 17.
 - HANDOVER MATERIAL
 - 18.
 - PROVISIONS ON INTELLECTUAL PROPERTY RIGHTS AND USAGE RIGHTS